Sail Loft, Portsmouth Naval Base

Home Case Studies Sail Loft, Portsmouth Naval Base

On the sail loft project there was a requirement to refurbish a 240m long redundant crane rail back to its former glory whilst maintaining access into the building and providing full encapsulation of the rail.

To achieve this, we erected the scaffolding in 4 rolling phases to provide continuity of program and cause minimal disruption to persons using the building whilst the works were being carried out.

Contact us for a free,
no obligation quotation

Make an Enquiry